PIB Press Releases

Shri Pralhad Joshi Chairs Consultative Committee Meeting on Jharia Coalfield Master Plan

Union Minister of Coal, Mines and Parliamentary Affairs Shri Pralhad Joshi chaired a meeting of the Parliamentary Consultative Committee of Ministry of Coal today in Parliament House to discuss the way ahead for Jharia Master Plan. Hon’ble MPs participated in the Consultative Committee meeting.

During the presentation, it was informed that due to unscientific mining in the pre-nationalisation period, mining areas in the Jharia coalfield area have faced problems of fire and subsidence. Now, these areas fall in the leasehold regions of Bharat Coking Coal Limited.

As an outcome of WP(C) No.381/97 filed by late Sri Haradhan Roy, Ex-MP in 1997 in the Hon’ble Supreme Court of India, a Master Plan for dealing with Fire, Subsidence and Rehabilitation in Jharia was approved on 12th August 2009 by Govt. of India with an implementation period of 10 years and pre-implementation period of 2 years. The implementation period ended in August 2021.

As a result of fire control measures taken by BCCL, the fire area is continuously decreasing and at present as per NRSC surveys in 2021 fire sites has been reduced to 18 sites covering 1.8 sq. km from the initial 70 sites covering an area of 17.32sq. km. At present, 15 sites are economically viable, wherein work related to the digging of fire has been awarded and at 2 sites BCCL board has recommended viability gap funding of Rs. 763 crores from the revised Master Plan. At 4 sites, blanketing will be done to cover the fire sites with a view to extinguish the fire.

Shri Pralhad Joshi Chairs Consultative Committee Meeting on Jharia Coalfield Master Plan
Photo credit-press release by PIB

Regarding rehabilitation, there are 595 sites wherein BCCL is responsible for taking action to shift its staff from BCCL houses. BCCL has undertaken the construction of 15852 houses and at present, about 3852 families are to be shifted to the new houses. BCCL has proposed 8000 houses to be utilised by Jharia Rehabilitation & Development Authority (JRDA) for non-BCCL families.

In the case of rehabilitation of non-BCCL families, there has been a substantial increase in the number of encroachers as of 2019 against the cut-off date provision of 2004. State Government is responsible for shifting legal & non-legal title holders. JRDA under State Government has taken up construction of 18352 houses out of which 6352 are completed and the rest will be completed by August 2022.

JRDA has prepared a revised rehabilitation proposal which State Government is examining. In the meantime, the Ministry of Coal has constituted a committee to examine the issue in detail and submit a report on the way ahead.

Disclaimer : This is an official press release by PIB.

Back to top button